Example production runs

What a first run in Turkey looks like.

Five worked examples, 100 to 300 pieces: the spec, the minimum, the weeks and a cost range from our calculator. Use them to plan your own brief.

Examples, not client orders

Two machinists at work on a sewing line in blue work coats
Operators on the sewing line
Supervisor leaning in to check a machinist’s work at a sewing station
Checking work at a sewing station
  • 2–4 wksSampling
  • 6–11 wksBulk, by product
  • 14 wksBefore a fixed ship date

Five examples

Pick a product, see the run.

Each example is a realistic first order worked through with our cost calculator and the lead times our factories work to. Your own quote comes from the factory, from your brief.

Example, not a client order

200 five-pocket jeans

  • Straight-leg five-pocket jean, one colourway, size run 28–36
  • Rigid cotton denim, zip fly, rivets and shank button
  • One rinse or stone wash, woven back label, care label, hang tag
Minimum
200 pcs per style (denim)
Sampling
2–4 weeks
Bulk
9–11 weeks from approved sample
First order, brief to goods
Plan around 10–15 weeks
Certificates
OEKO-TEX, GRS (some factories)
Machinist sewing indigo denim panels at a single-needle machine
Production step: Sewing denim panels. Not this run.

Calculator range per piece

$30.15–$51.75

× 200 pcs = $6,030–$10,350 ex-factory, USD

Inputs: 22–40 base · Mid fabric · 100–300 (×1.20) · Standard construction · extras Wash/dye treatment $2.50, Custom woven labels $0.60, Care & size labels $0.30, Hang tags $0.35 (+$3.75/pc)

What moves the price

  • Denim weight and stretch, and where the fabric is milled
  • The wash recipe: a rinse costs less than stone, bleach or distressing
  • Hardware: branded buttons and rivets add cost and lead time

Example, not a client order

300 fleece hoodies

  • Pullover hoodie, 3-panel hood, kangaroo pocket, rib cuffs and hem
  • Brushed-back cotton-rich fleece, one colourway, size run XS–XL
  • Chest embroidery, woven neck label, care label
Minimum
100 pcs per style
Sampling
2–4 weeks
Bulk
6–8 weeks from approved sample
First order, brief to goods
Plan around 10–15 weeks
Certificates
GOTS, OEKO-TEX (some factories)
Close-up of hands guiding a dark jersey garment through an overlock machine
Production step: Overlocking a dark jersey garment. Not this run.

Calculator range per piece

$16.70–$26.70

× 300 pcs = $5,010–$8,010 ex-factory, USD

Inputs: 14–24 base · Mid fabric · 300–500 (×1.00) · Standard construction · extras Embroidery $1.80, Custom woven labels $0.60, Care & size labels $0.30 (+$2.70/pc)

What moves the price

  • Fleece weight (gsm) and organic or recycled content
  • Decoration: embroidery stitch count, or print instead
  • Garment dye or a wash adds a step and cost

Example, not a client order

150 merino sweaters

  • Fine-gauge crew-neck sweater, fully fashioned
  • Merino wool yarn, one colourway, size run S–XL
  • Woven neck label, care label
Minimum
100 pcs per style
Sampling
2–4 weeks
Bulk
6–8 weeks from approved sample
First order, brief to goods
Plan around 10–15 weeks
Certificates
GOTS, OEKO-TEX (some factories)
Stacks of green, cream and mustard knitwear between operations on a busy production floor
Production step: Knitwear stacked between operations. Not this run.

Calculator range per piece

$25.38–$41.70

× 150 pcs = $3,807–$6,255 ex-factory, USD

Inputs: 12–20 base · Luxury (tencel, wool, silk) fabric · 100–300 (×1.20) · Standard construction · extras Custom woven labels $0.60, Care & size labels $0.30 (+$0.90/pc)

The calculator has no knitwear category yet. This uses the nearest one (sweatshirt base) with the Luxury (wool) fabric tier, so treat it as rough.

What moves the price

  • Yarn: merino grade and blend (cashmere blends cost more)
  • Gauge and knit structure: finer gauge and cables take longer on the machine
  • Linking and finishing by hand on necklines

Example, not a client order

100 linen dresses

  • Midi dress with a lined bodice, side zip and waist seam
  • Linen woven fabric, one colourway, size run XS–XL
  • Woven neck label, care label
Minimum
100 pcs per style
Sampling
2–4 weeks
Bulk
7–9 weeks from approved sample
First order, brief to goods
Plan around 10–15 weeks
Certificates
OEKO-TEX, GOTS for linen (some factories)
Machinist sewing a black woven garment on a post-bed machine
Production step: Sewing a black woven garment. Not this run.

Calculator range per piece

$28.98–$60.18

× 100 pcs = $2,898–$6,018 ex-factory, USD

Inputs: 18–38 base · Upper-mid (organic, Turkish mills) fabric · 100–300 (×1.20) · Standard construction · extras Custom woven labels $0.60, Care & size labels $0.30 (+$0.90/pc)

What moves the price

  • Linen quality and whether it is pre-washed
  • Lining, seams and closures: every panel adds sewing time
  • Small runs carry more pattern and sampling cost per piece

Example, not a client order

150 padded jackets

  • Hip-length padded jacket with hood, zip front and two welt pockets
  • Woven shell with synthetic padding and a lining, one colourway
  • Woven label, care label, hang tag
Minimum
150 pcs per style (outerwear)
Sampling
2–4 weeks
Bulk
9–11 weeks from approved sample
First order, brief to goods
Plan around 10–15 weeks
Certificates
bluesign, GRS (some factories)
Checking rolls of checked flannel fabric on a storage rack before cutting
Production step: Inspecting flannel fabric rolls. Not this run.

Calculator range per piece

$53.75–$113.75

× 150 pcs = $8,063–$17,063 ex-factory, USD

Inputs: 35–75 base · Mid fabric · 100–300 (×1.20) · Complex construction · extras Custom woven labels $0.60, Care & size labels $0.30, Hang tags $0.35 (+$1.25/pc)

What moves the price

  • Shell fabric and padding type (synthetic or down)
  • Construction: quilting, baffles, taped seams, trims
  • Zips and hardware, which also set part of the lead time

All five are examples, not client orders. Ranges are ex-factory in USD from the calculator’s benchmark logic; freight, duty and VAT come on top. Timings are the lead-time ranges for each product family, with the conservative end shown.

How we quote

From an example to your own number.

The examples give you a corridor. Four steps turn it into a written price from the factory that will make your run.

Two people reviewing a mustard garment at an inspection table
Reviewing a garment during inspection
  1. 01Day 0

    You send the brief

    Product, pieces per style, target date, where it lands. A sketch or photos are enough to start.

  2. 02Within 24 hours

    We read it and reply

    Fit or not, what is missing, and a ballpark from the same benchmarks as these examples.

  3. 03About a week

    The factory quotes

    The factory in our group built for it quotes from your spec: price per piece, sampling cost and lead time.

  4. 042–4 weeks

    You approve a sample

    Pattern to first sample 10–14 days; 2–4 weeks with corrections. The bulk price is fixed on the approved sample.

Behind the examples

The floors these runs would go to.

Each example is placed by product family: denim with a floor that works with a laundry, knitwear with a knitting floor, wovens and prints with their own lines.

  • Carts loaded with washed jeans in front of a row of industrial washing machines

    Jeans on laundry carts

  • Operator checking a computerised flat knitting machine on a knitting floor

    Flat knitting machine

  • Wide sewing floor with long lines of operators at their machines

    A wide sewing floor

  • Brightly printed fabric coming off a wide fabric printer

    Printed fabric, ready to cut

  • Worker smoothing a grey knitted sweater flat on a steam press table

    Pressing a knitted sweater

Examples, not client orders. Photos show production steps in Turkey, not one specific factory.

FAQ

About these examples.

What they are, where the numbers come from, and what they leave out.

Still not sure it fits?

Send the product, the quantity per style and the date. We reply within 24 hours with an honest answer. Send a brief
oneaimapparel@gmail.com

No. Each one is an example, not a client order: a realistic first run worked through with our cost calculator and the lead times for that product family. We do not publish client orders or client names.

From the same logic as our cost calculator: a benchmark range per garment, multiplied by fabric tier, quantity and construction, plus per-piece extras. The inputs are listed under each range. The factory’s written quote is the number that counts.

We show the conservative end. Sampling takes 2–4 weeks and bulk 6–11 weeks depending on the product, so plan around 10–15 weeks from brief to goods for a first order. With a fixed ship date, start at least 14 weeks before it.

Most factories in our group start at 100 pieces per style; denim and activewear at 200, outerwear and tailoring at 150. Below that you are usually looking at small-batch producers.

No. They are ex-factory (FOB) in USD. Freight, clearance and import VAT come on top. Into the EU, goods with an A.TR certificate usually enter without customs duty; the UK has its own rules of origin. Check with your broker.

Send a brief

Tell us what you’re making. We’ll find the line that makes it.

Four things are enough to start. We reply within 24 hours and place the brief with the factory in our group built for your product.

  • Product and fabric
  • Pieces per style
  • Date you need stock
  • Where it lands: EU or UK

Free to send · No commissions · The factory bills you directly

Operator in a work vest handling a garment on a long, brightly lit sewing floor
On the sewing line